Manufacturing Order Details For Worker
This page is a detailed production reporting view for the worker. The page is accessible from:
- My production plan section when opening a Manufacturing Order details.
- Production planning -> Manufacturing orders -> MO details by pressing Go to production.
Jump to:
- Starting and finishing:
- Quantity of processed products:
- Used materials:
- Visibility of other operations.
Recording the progress of operations
- Scroll down to the Operations section and find the operation line.
- Press Start Start to start work.
- Press Pause Pause if the operation is stopped, but it is not finished yet.
- Press Finish Finish when the operation is fully completed.
The button press times are recorded and accordingly, the actual labor hours are calculated.
Finishing the Manufacturing Order
- Finish all operations.
- Press Finish production on top of the page.
- If all parts have been consumed, the system will mark the manufacturing order as done.
- If some parts have not been consumed, then two options will be presented:
Consume all – consume all booked parts.
Release unused – bookings will be canceled. A note will be added to the MO stating the difference between planned vs reported materials.
After making a decision, press Finish production again.
Reporting the number of processed products
- Start an operation.
- When you press the Pause Pause or the Finish Finish button the software will ask you how many items were completed from the last start.
- Enter the quantity.
- If the operation has been stopped several times, make sure to enter the quantity from the last start.
- If there are additional or side-products defined in the BOM, also report the quantities of these that should be placed in stock.
Reporting over- or underproduction:
- Enter the actual quantity of products, when asked.
- If the reported quantity of the final operation differs from the initially planned quantity, the software will display a confirmation dialogue. If confirmed, the quantity of the MO is updated.
- The MO quantity can also be updated by the production manager at any time.
- See also: Sub-assembly overproduction in a multi-level MO.
Reporting used materials
Materials consumption can be reported in bulk while finishing the Manufacturing Order.
To report materials consumption individually:
- Press Consume Consume next to the part.
- Or scan the item or stock lot barcode.
- Enter the number of used parts.
- If the quantity is greater than what is booked, extra will be taken from stock.
- To undo consumption, enter the quantity with a negative (-) number.
To report materials consumption in bulk, according to the number of finished goods:
- Press Consume parts for end-products above the materials table.
- Enter the number of finished goods.
- The software consumes all booked parts proportionally.
Consumed quantity = Entered quantity x (Booked quantity / MO planned quantity) - When the "Packing" functionality is used, the packaging will not be consumed automatically. It must be consumed manually.
- The software consumes all booked parts proportionally.
Adding materials to the MO
If some additional part, that was not on the list of materials, has been used:
- Press the Add a booking (+) on the top right corner of the Parts list.
- Select the part.
- Enter the quantity.
-
If Tracing is enabled, you will see a list of available stock lots to choose from.
Enter the desired quantity next to each stock lot you wish to book.
-
If Tracing is enabled and you want to book materials from a specific stock lot:
- Press the Increase booking (+) on the material's line.
- You will see a list of available stock lots to choose from.
- Enter the desired quantity next to each stock lot you wish to book.